Skip to the content.

Offensive Lens Assessment —

   
Assessment ID  
Engagement ID ENG-__--___
Assessed  
Lens version 0.3.0
Overlay version assessed against v____
Environment  
Scope note  

Verdicts are not portable across overlay versions that change the ladder or the evidence set. Record the overlay version or the report expires silently.

1 · Verdict summary

Lens Control validated Verdict Techniques run PASS PARTIAL FAIL N/A
L1 Inventory Drift 1 · Inventory            
L2 Containment Bypass 2 · Safe Modes            
L3 Evidence Starvation 3 · Evidence            
L4 Recovery Re-entry 4 · Controlled Re-enable            

A lens is VALIDATED only when every applicable technique is PASS.

2 · What this means for incident response

Written for the person who will make the materiality call, not for the engineer who will fix it. Answer directly:

3 · Findings

One subsection per finding. Mirror the finding schema, maintained with the lens source.

— ·

   
Lens / control  
Severity  
Defensive signal fired / late / absent / unattributable
Write occurred  
Overlay playbook  

Observed: what happened, factually, with no interpretation.

Evidence: class, locator, redaction status, hash.

Why it matters. The incident question this makes unanswerable, or the write path it leaves open.

Remediation: the control change, not the symptom fix.

4 · The six-class evidence grid

Report L3 as a grid, not as a verdict list. This table is what tells a CISO which incident questions are unanswerable today.

Evidence class Present Complete Survives containment Attributable Retention vs. discovery latency
Prompts / responses          
Tool-call records          
Retrieval traces          
Memory state          
Configuration state          
Identity / downstream audit          

5 · Residual blast radius

From OL-T207. State it as a number, because the runbook should.

   
Agent sustained action rate  
Measured containment latency (under load)  
Residual actions before containment is effective  
Runbook’s claimed figure  

6 · Remediation priority

# Finding Control change Owner Target date Re-run technique
1          

Every row ends with a re-run. A remediation without a re-run is an intention.

7 · Canary disposition

Marker Introduced Removed Confirmed absent from retrieval / memory / write targets
       

8 · Limitations

State plainly what was not tested and why: techniques deferred on write risk, N/A techniques and their rationale, environments out of scope, and whether staging is representative of production. A reader who cannot see the boundary of the assessment will assume it has none.